Lake Tyee Board Meeting Minutes
Saturday, September 26, 2009 at 9 a.m.
Lake Tyee Manager’s Office
Called to order at 9:10 a.m. by Peter Coates
Board Members Present: Peter Coates (PC), Janet Walsh (JW), Janet Legg (JL),
Paula Ratcliff (PR) and Jean Johnson (JJ)
Additional
Attendees: Marlene Lounsberry (ML) of CDC
Approval of Minutes:
August 22, 2009 Board Meeting minutes (JL motioned, 2nd PC) to approve minutes (MSC all); September 19, 2009 Special Assessment
Ratification Meeting minutes (JL motioned, 2nd PC) to approve minutes (MSC all). August 2, 2009 Executive
Session minutes not received by ML. PR to re-send. (JJ motioned, 2nd PC) to table until October board
meeting (MSC all).
Manager’s Report: CDC submitted
a report of action items and a financial narrative (attached).
Executive Session: requested by Marlene regarding fines
Contract renegotiation with CDC: asks that we move forward on this
Meeting with Attorney to Change Governing Documents: Marlene
will contact
attorney to meet with board 10/23 at 1 p.m. or 10/26 at 10 a.m.. CDC to email response
to Board regarding date/time.
Hearing Committee for Violations: PR to put on agenda for October.
ML will set date of meeting and contact lot owners. PC will coordinate.
Trail Signs: will no longer be mailed out by CDC.
Board Packets: CDC will send board packets electronically one week
in advance of board meeting. A printed version of financial reports will be provided to Treasurer.
carrier. Group Health rate
is going up 23%. Group Health cost for medical only is $537.20 (LT) and $161.16 (paid by full-time employee).
CDC’s insurance for medical/dental/vision is $497.19 (LT) and $133.76 (paid by full-time employee). CDC medical-only
plan is $445.88 (LT) and $133.76 (paid by full-time employee). Barb advised that CDC will be going through their renewal
period in 3-4 months. Marlene will check to see if we will be locked into a 12-month contract if we switch employees
to CDC’s insurance. Peter suggested we stay with Group Health plan and see if something else comes along in the
mean time. This item needs to be discussed in August next year.
Boat
Policy: to be posted on website and gates. After 10/31, boats with lot number will be taken to lot and
owner charged $25. Others will be taken to storage and charged $25 to reclaim their boat.
Off-Season Office Hours: Friday (2-6p.m.), Saturday and Sunday (10a.m.-2p.m.).
Marlene would like to staff the office 5 days/week despite limited office hours for lot owners. She also needs an Administrative
Assistant. Marlene emailed job descriptions to Peter. New hours to be posted on website by CDC. It was suggested
by JW that if an event occurs (water outage, power outage, etc) that the info be posted outside of office door so lot owners
do not need to enter the office and ask for the information. Marlene advised board that if a lot owner comes to Lake
Tyee, their key does not work and office is closed, Tammy allows them in the gate based on the delinquency list she has.
Comfort stations that are to remain open this winter will be cleaned Friday and Sunday only.
Security Staffing: do not add additional security.
Service Level Performance: Executive Session requested after October Lot Owner
Meeting adjourns. Attendees: Board, Anita, Marlene and Morgan. ML to advise Anita that the meeting will
probably take place around 11 a.m.
Bank Signature Cards:
Need minutes designating officers of Lake Tyee and who signers are. CDC will FAX minutes to Darcy at Summit Bank.
Since Joann Binkley resigned, her name is to be taken off bank signature card.
Signators will be Peter Coates, Janet Walsh, Janet Legg and Paula Ratcliff
Board Meeting adjourned at 9:55 a.m. for Lot Owner Meeting. Board Meeting reconvened
at 11:50 a.m.
Committee Reports
Electrical: Peter Coates suggested the length of the project may need
to be shortened
Treasurer’s Report for
August, 2009 (Janet Legg):
General
Operating Account Balance $79,351.90
Accounts
Payable $42,749.35
Replacement Reserves
$338,029.28
Assessment Receivables
$150,625.79
Delinquent Accounts
58 are in lien status for a total of $113,271.78
Foreclosure on 1 lot
Peter advised Board that the cost to
repair ground wire from shop to CS #8 will cost $100,000+ and asked Barb how we can pay the repair. Barb referred Peter
to the Statement of Reserves Schedule from the 9/12 meeting which as of 7/31/09 showed a balance of $54,000 in unallocated
reserves. We would need to take into consideration activity for August and September to determine what is still available.
The 7/31/09 balance in the electrical project reserves will be $225,000 once the $70,000 transfer is made from operating to
reserve related to the 2008 electrical project. The electrical reserve will be funded with an additional $29,470 in
both August and September, provided funds are available, which will bring the balance up to $314,000. Pat provided an
estimated expense for 2009 of $264,000 which would then leave $50,000 available, provided there are enough funds to transfer
the $70,000 from operating and to fund the $29,000 in August and September. Barb also indicated there were some potential
coding reclassifications needed in the general ledger from operating to reserve which would impact the balances. Barb
requested Marlene look at the expenses coded to the following accounts to determine if some need to be reclassed within proper
operating accounts or need to be reclassed from operating to reserve and to ensure the reclassifications were complete in
the September financial statements:
7050-000 General Maintenance and Repair
7403-0000 Shop Supplies
7560-0000 Equipment Maintenance and Repair
6300-0000 Water System Repair and Maintenance
6400-0000 Septic System Repair and Maintenance.
Bill Aldrich advised her that $25,000 can be repurposed from lake reserve. The Board’s concern
is that we are able to pay all of our bills in a timely manner. Barb suggested to Peter that lot owners who can pay their
assessment prior to November 15 should be encouraged to do so. Marlene will contact Anita to have the following insert
in the October mailing: “Because the Board’s desire is to meet our financial obligations in a timely manner,
we request that lot owners who are able to pay their assessment now to please do so”.
Proceeds from sale of Lake Tyee owned lots go into 2009 Operating Fund.
Unfinished Business
Website Design: (Colleen McKnight) presented a proposed web design to the Board.
She advised that Diane Askins would design the sight and will compare host rates for us. Peter requested there be a
secure ID# for ‘Member Only’ page. Diane’s website is netclimberwebdesign.com. Janet Legg will email the board with sites Diane has designed. We are to ‘reply all’ with any comments.
After review, Diane will give us an initial proposal and we will move forward from there.
New Business
Lot
Line Adjustment 2F7: (ML) Mr. and Mrs. Bordeleau had their lot surveyed and found that
¾ of their lot is in the road. They would like the center pin moved to reflect the survey. Marlene will
write a letter to Skagit County advising them that the board has accepted pin relocation and surveyor will send paperwork
to county. Copy of letter to go into lot owner file.
Committee
Reports continued…
Recreation &
Social: Barb Thibert advised that Angel Hanson is the Social Director. Janet Legg will be the Board liaison.
Barb advised the yard sale with items donated from lot owners raised $348.50 and she announced Halloween Party festivities
for 10/24. The Recreation & Social Committee bank signators will be Angel Hanson and Janet Legg. Angel would like
to close the Summit Bank account and open the social bank account at a larger bank to facilitate depositing cash after events.
Summit Bank is inconvenient for her.
PR will email minutes to Darcie
at Summit Bank. JL agreed to pick up the signature cards for all of the Lake Tyee accounts.
Grounds & Maintenance: Peter Coates will be Board liaison on this committee.
JW will forward to him email addresses of committee members.
Building
& Covenant Committee: (Jean Johnson) JJ will call a meeting of her volunteers this week to get a
chairperson and hearing committee together. ML advised her that 3B118 requests a hearing on Sunday, 10/25 at 10 a.m.
ML discussed the complaints received about LandsWest and the development
of their lots. PC will speak to Ed and Kareese about coordinating with her whenever they develop a lot. JJ will
contact Skagit County about fill and grading permits. ML requested that a better permit application be drafted by the
Building & Covenant Committee that would include all county restrictions as well as grading/landfill requirements.
Lake Tyee is responsible for the maintenance of septic holding tanks and drain fields that can be damaged if requirements
are not followed.
Budget & Finance Committee:
Year-to-Date Report (attached): (Barb Thibert)
Number on Report:
#21 – $3000 past due, payment arrangements of an additional $300/month were made but is now two months
late on payment arrangements. ML will determine status from June-September with Wendy. ML will advise JL and she
will advise board.
#29 - Marlene
believes there is about $500 to be deposited. September has not been
counted
yet.
#67 - Diane Johnson advised
that it will cost us more to get out of contract with the copier and postage meter.
#70 – Barb advised there may be $10,000 left over
#97 – ML to check if some of this can be reclassed from operating fund to road reserve.
#99 – Comments are prior to latest outage repair. Some can be reclassed to electrical
reserve as it was paid out of operating fund.
#102 – culverts shouldn’t be under equipment maintenance.
Peter Coates left meeting in the hands of Janet Walsh.
2010
Budget - Barb requested the board advise on the format they desire to present to the owners so a draft can be prepared
in that format. Does the Board want it at the level of detail currently being reviewed or at a summary level?
If summary, how summarized?
2010 Budget decisions made:
Reserves:
Electrical $40,000
Replacement of maintenance vehicles $15,000 (one small 4x4 pickup and a small vehicle
for comfort station cleaning
and meter readings).
Insurance deductible and small claims $0.00
It was decided that items listed between Road and Key Access to Pool are items that
money can go towards as delinquency
money comes in.
Line Items:
#10 – discount of $50 per lot
#15 – proceeds should be about $10,000
#28 – ML to have ice machine removed
#29 – Increased to $1200
#63 – 2.5% CPI Increase
#66 – reduced to $2500
#72
– contact Carol Trowbridge about past Reserve Study. ML to get bids.
#76 – reduced to $300
#77 – offset by rental income
#79 - $3000 is the cost of classes only (does not include salaries). Classes are required.
#80 - $0.00
#86 – ML will contact Attorney to see if there is a way to charge a handling fee for
-
credit card users. Otherwise, we can give lot owners a list of other payment options
available.
#92 –
ML will check on this figure
#93 –
reclass $800 for 2009
#95 – ML
has someone who will take vehicles for free.
#97 – needs to be reclassed to reserves for 2009. ML feels this is a great need
#105 - $0.00 use volunteers and donated plants
#117 – still looking to make changes here
#119 – ML to check on 2009 figure
#132 – Since lake is in good shape and fish are holding over, this amount could be
reduced to $2000.
Derby proceeds go towards fish purchase as well.
#133 - $0.00
Staffing & Salaries:
Board requested job descriptions before decisions can be made here. Some suggestions
were:
-
- Security should man the gates to save on gas and wear & tear on vehicles.
- Comfort Stations are currently cleaned five days a week May-September. We have 16 comfort
stations. A full-time employee has 30 minutes to clean each comfort station. JJ to check with County to see if
we really have to keep all 16 open.
- Admin Employee 2: ML would
like this to be a seasonal position (April-September 40 hrs/wk).
The Board agreed to provide Barb a revised Salaries and Wages budget by Friday, 10/2/2009 after reviewing job descriptions
and having discussions amongst themselves.
Lake Tyee Electrical
Upgrade Assessment Payment Options were passed out to all the board members for their review.
Waiving of Fines: since due process was not followed a motion was made
by JL to waive fees, 2nd PR (MSC all) A motion to waive Jerry Robinson’s fines because due process
was not followed was made by JL, 2nd PR (MSC all).
Tree Removal:
Bill Aldrich wants to remove ‘danger trees’ on his lot now and charge us for that work in 2010. Staff to
look at trees. JW advised he is to hire an arborist at his cost and then the board will make a decision based on arborist’s
report.
Electric Meter (2C59):
in the middle of their lot and they would like it moved. ML will contact Pat Sweeney or Rheema.
Nominations to fill two vacant board positions – we will email our
thoughts on this.
Tabled
Live-Ins
Meeting adjourned 4:30 p.m.
Paula Ratcliff
Board Secretary
MEETING MINUTES
Lake Tyee Board Meeting MinutesSaturday, August 22, 2009 at 9 a.m.Lake Tyee Manager’s Office Called to order
at 9:10 a.m. by Peter Coates Board Members Present: Peter Coates (PC), Janet Walsh (JW), Janet Legg (JL), Paula Ratcliff (PR) and Jean Johnson (JJ)Board Members Absent: Roger and Joann BinkleyAdditional Attendees: Marlene Lounsberry (ML) of CDC Additions/Approval of Agenda: Minutes of the July 25th meeting approved as amendedAdditions: LandsWest/Kareese, Bank Signature Cards
(Jean), Electrical Outages (Paula) Announcement by Peter that after lot owners meeting, the board will go
into Executive Session with a property owner who has requested to meet with the board. Electrical
Project Update: Pat Sweeney asked that we take his report
“Lake Tyee Medium and Low Voltage System Rebuild” (attached) into consideration for the 2010 budget.
Pat commended Dave Renzelman for his help with the electrical project, finds his knowledge invaluable and believes
his participation is a cost saver. Manager’s Report: CDC submitted a report of action items and a financial narrative (attached). Marlene
introduced the new Doug the new foreman.
Vehicle Decals: previous policy is now being adhered to Tree
Removal: problem with Mountain Beavers probably eating tree roots. Roads:
they’ve been graveled and seed can now be spread on sides of roads. Insurance:
concrete building needs to come down resulting in no equipment
storage this winter. She will find out date it needs to be removed. Water
Outage: generator will be moved closer to pump and bids to do so are in
process.
Laundry Room Door: new lock mechanism is needed and Gateway will be
contacted.
Lot in Meadow: was purchased as-is but owner wants to be hooked up to septic.
Marlene proposed we locate septic but lot owner would be financially
responsible to hook up to it.
Lake Owned Lots: she will email board with these. Fines:
requested that fines issued without due process be reversed. Attorney:
wants to set a date to meet. Peter will advise CDC. Website Updates:
Peter will work directly with Anita and forward
information/updates to her. He will monitor site on a daily
basis. Board Meeting adjourned for Lot Owners Meeting, followed by Executive Session.
Board Meeting resumed at 1:12 p.m. LandsWest: Kareese would like a new process for getting
fees to title companies. Her reasons: 1. CDC uses Condo Search who
is not liable if closing is delayed. 2. If deals fall through, Lake Tyee
will be legally responsible. 3. Their fees are a burden to buyers and sellers.
They want all fees up front ($90), an additional $50 to close on time and an additional fee is issued to cancel.
4. This should be a source of revenue for Lake Tyee, not CDC or Condo
Search. 5. She will not advise any buyers to use Condo Search as they would be giving
their rights away.She also advised board that electrical
meters are not being read at closing and believes the entire process can be completed in-house. She requested
this issue be considered as an item for contract renegotiation. Committee Reports:
Recreation & Social – Angel Hansen nominated as Chairperson
Grounds & Maintenance – no report
Budget & Finance (Barb Thibert)
Lots Sold: one on contract
Audit Status: waiting for history from 2007. Info needed from
IRS
showing corrected Tax ID number. Needs
2008 audit so
accurate information is given to lot owners on 9/12.
Accounts Receivable on mobile home - Marlene will check on it.
Assessment – justification for assessment is rate of delinquencies and
unknowns from 2008.
Budget: Roger still has figures to give her for budget. Unfinished
Business Special
Assessment: Janet Legg made a motion to assess each lot $400,
second by Janet Walsh. Peter amended motion to include: that the assessment will be
spread out over two payments of $200 and that any left-over money would go into Reserve Fund. Janet
Walsh agreed to amended motion. Motion made by Peter to set date for special assessment meeting per Bylaw
8.10.1: 9/12 Special Assessment & 2010 Budget Q&A Meeting; 9/19 Special Assessment
Ratification Meeting. Peter will prepare a letter to the lot owners and email the board for review.
The letter and ballot will then be sent out to lot owners. The entire $400 assessment will be due
by November 15 and late on November 30. JW asked what a member in good standing is? Marlene
to contact attorney. PR read definition from bylaw 4.5.1. Mailing of Trail Signs and Minutes (Jean): New policy
is in effect 1/1/2010. There
will be a link on website to access Train Signs and Minutes or copies will be available in the office. Dues payments mailed directly to CDC (Janet Legg): inform
lot owners at September 12 meeting Credit cards no longer accepted (Janet Legg): inform lot owners at September 12 meeting Policy for Facility Use
by Staff (Peter): Motion made by JW to not allow employees
use of Lake Tyee amenities. JJ seconded motion. Discussion between Marlene and
Board. PR suggested the issue be brought up before the lot owners at the September 12 meeting.
Motion by PC to table until 9/12 meeting with lot owners, JW agreed. Passed. Building Permit Approvals/Disapprovals: to be done
by Marlene or staff designee. Pool:
Marlene advised that additional electrical bids in process New Business Bank Signature Cards: (JJ) handed out CIP forms for bank signatures:
Peter Coates, Janet Walsh, Janet Legg, Paula Ratcliff and Joann Binkley. It was advised that Roger
shouldn’t be on card as Joann is. Power Outages: (PR) If there is a power outage over 6 hours long; signs
will be posted at all the gates. Live-Ins: Marlene advised there is a 210 day limit
on each lot owned. She has not found letter that had been sent to lot owners previously. (JW)
advised there should be an annual notification of the 210 day rule. Target those who we think are residing
here and check their data records. (ML) suggested a problem with the reports generated. (PR)
suggested contacting Gateway for additional training or allowing Dennis Johnson to help in retrieving necessary information.Discussion of lot owners who have been volunteering in lieu of paying
dues. (PR) commented that with the financial crisis we are in, we can no longer allow this practice to
continue. Those lot owners need to be informed that as of January
1, 2010, they will be paying dues. Meeting adjourned 4:45 p.m. Paula RatcliffBoard
Secretary
Draft January Board meeting minutes
Draft
Lake Tyee Board Meeting Minutes
Saturday, January
23, 2010 at 10 a.m.
Lake Tyee Manager’s Office
Called to order at 10:35 a.m.
by Peter Coates
Board Members Present: Peter Coates (PC),
Janet Legg (JL), Janet Walsh JW), Michael Bansemer (MB) and Allen Ward (AW)
Board Members Absent: Paula Ratcliff
Additional Attendees:
Marlene Lounsberry (ML) of CDC Management
Agenda:
Motion to approve January 23, 2010 Agenda (JW motioned, 2nd JL) (MSC all).
PC announced
that the Board will have an executive session today to discuss legal issue
Approval of Minutes:
Motion to approve December
19, 2009 Board Meeting Minutes as amended (JW motioned, 2nd JL) (MSC all).
Motion to approve December
19, 2009 Executive Session Minutes (JW motioned,
2nd AW) (MSC all)
. Motion to approve January 7, 2010 Special Board Meeting Minutes (AW
Motioned, 2nd
JW) (MSC all).
Manager’s Report: (CDC submitted
a report of action items and a financial narrative (attached):
·
First manager/lot owner meeting was held January 10th.
·
Audit Draft has been received for review.
·
Quit Claim Requests received from lot owners.
Information received from the attorney. Ledgers
are attached.
·
Summit Bank Change of address needs to be completed.
Need to resubmit signature cards for the Operating and Reserve accounts. Recommends that
bank statements should go directly to CDC.
· Work Camper – summary provided. Plan to submit blanket application by February 10th for security, pool, administrative assistants. Need to establish which lots to provide Work Campers
which include all utilities (full hookups) using reciprocal lots or Tyee owned lots.
·
Electricity billing cycle needs to be decided - bi-monthly or
continue being mailed monthly.
· Playground
equipment needs to be replaced due to unsafe conditions. Does not meet playground regulations.
·
Special Assessment mailer was mailed.
·
Copying of Board packets discussed. Treasurer to receive
hard copies.
·
ML recommended writing off old bad debt on lots that may be deemed
uncollectible.
Treasurer’s report for December,
2009 (JL):
·
General Operating Account balance: $167,745.15
· Accounts Payable: $20,939.27
·
Prepaid Assessments: $23,428.47
· Bank Loan on Mobile: $30,116.47
·
$295,439.10 is due to Reserves from Operating and $226,394.24 due to Operating
from Reserves (these were balance forward entry corrections made when the three sets of 2008 books were reconciled into one).
The difference of $69,044.86 is what Operations owes Reserves except that as of 12/31/2008.
· Replacement
Reserves – Maintenance Reserve account balance: $148,170.48
· Assessments Receivable: $243,782.61
· Delinquent Accounts: 91 accounts at the attorney; 89 have liens filed
·
Major Expense Items of note for December: Year-end
labor was $15,364 less than budgeted. Year end maintenance expenses were $15,158 more than budgeted.
·
PC asked the Treasurer and Budget Committee
to review and make recommendations regarding possible write-offs of old bad debt on lots which could be deemed uncollectible.
·
Accruals: JL requested that CDC accrue all 2009 outstanding invoices to be paid
out of 2009 funds.
·
Recommended adding to Agenda a review of the draft 2008
Audit under New Business.
Committee Reports:
Electrical Upgrade
Project Committee: Meeting
scheduled February 6, 2010 to vote on the Special Assessment for the electrical upgrade project.
AW reported that a meeting is scheduled Friday,
January 29, 2010 in the Lake Tyee office
to discuss the upgrade current plan
and alternatives
Recreation & Social Committee: Barb Thibert reported that a Bingo license will
not be required because Tyee is a private club (no public attendees) and does not exceed
$5,000 in proceeds during the year. Annual Calendar of events will be posted on the website for the entire
year.
Grounds & Maintenance
Committee: PC will call
for a meeting of the committee and JW or Bill Aldrich will notify members. Work Campers and lots owned
by Lake Tyee need update. Proposed meeting for February 13th.
Building and Covenant Committee: New board liaison needs to be named. Two board members required. Paula will remain Board Liaison. PC volunteered to be the other board liaison.
ML suggested that the committee create a building permit application form; ML will
provide a list of recommendations to the Board for
form creation.
Budget and Finance Committee: Barb Thibert provided the following four schedules and comments on each (see attached): 2009 Operating Income and Expenses; Statement of Reserve and Liquidity analysis; AR analysis; and Invoices from Waste Management).
·
Committee recommends that the Board approve an allocation adjustment to move $4,535 from Unallocated to
Electrical System Repairs
·
2.7% overspent over 2009 budget
·
Reported 99 lots have balances between $200-$400, indicating they have only paid part of
the special assessment to date
·
Waste Management monthly fee invoices have not been reduced to winter rates and needs review
·
Accruals are needed for 2009 expenses
·
Schedule needed for reserve study
·
Recommend not to write-off bad debt (need
to know all associated costs at time of foreclosure).
·
$15,000 from 2008 needs to be removed from operating to reserve
·
Bi-monthly billing needs more investigation prior to changing
monthly billing
Unfinished Business:
Audit
of 2008: The draft
2008 Audit has been received. Letter Of Representations needs signatures and mailing to CPA
company of Cagianut & Company in order to receive final 2008 audit.
Audit Engagement Letter for 2009:
Letter of engagement obtained; needs signature by President to initiate 2009 audit.
Discussion to obtain 3 bids occurred with decision to continue with the same CPA company. Motion made to engage the CPA company of Cagianut & Company to conduct the 2009 Audit (motioned
JL/ AW 2nd
) (MSC) .
Electrical
Upgrade Special Assessment:
AW reports that there is a meeting scheduled Friday, January 29, 2010 to discuss current project plans and alternatives.
Will proceed with meeting and vote on February 6, 2010.
Interest Rate on Mobile: JL reports that Summit Bank has agreed to reduce the manager’s
trailer loan from 10.5% to 8% and has been sent accounting documents by CDC Management as requested.
Quit Claim in Lieu of Foreclosure: Attorney opinion letter received in response to details
requested on quit claim deeds. JW will obtain quit claim forms and investigate further.
Web Page:
Colleen McKnight suggested a
website sub-committee be formed including the Board and lot owners.
Website Policies “For sale by lot owner” Policy
#12 and Privacy Policy #13 were provided to the board for review
and were tabled until February board meeting.
Bi-monthly electrical Billing: Motion made to rescind the bi-monthly
billing and continue to bill lot owners monthly (Motioned JL/MB 2nd) (MSC all) .
Work Campers: February 10TH is deadline for providing advertisement. Need to identify which lots (all with full utilities) will
be needed and utilized. 2 reciprocal lots
identified for Work Campers as well as lake tyee owned lots for sale.
Covenants: AW reports no meeting of this committee has occurred recently but will be scheduled soon. AW spoke with Ed Forshee of Lands West who suggested a meeting with
the attorney for Skagit county to discuss the 1996 covenants which were never adopted due to oversight, We need to explain to the attorney that for some time the 1996 covenants are what is being
handed out by the title company to new land owners and get him to
sign off on them. Ed agreed that he would be willing to sign any necessary documents required by the attorney.
NEW BUSINESS:
Visa Rate: Reduced
user fees investigated by Jean Johnson, but no report
received. JL will further investigate.
Petition to remove Board: Original Petition For
Removal and Replacement of the Board Of
Directors was received by the board and recorded in minutes. Meeting to vote scheduled
for February 6, 2010.
Transfer of funds in Reserves:
Motion made to transfer $4,535 from the Unallocated Reserves into the Electrical
System Repairs Reserves. (Motioned JW/AW 2nd) (MSC all).
Establish Sub-Committee:
Motion made to establish a communications sub-committee that will make recommendations to the
board for the webpage and communications to the membership. (Motioned AW/JW 2nd)
(MSC all).
Next
Month’s meeting: February
27, 2010
Meeting adjourned at : 1:22 p.m. for Executive Session
Meeting reconvened at: 2:55 p.m.
Motion made to fill the vacant
Board Position (Motioned MB/AW 2nd). Unanimously failed.
Motion made to accept four lots quit claim deeded back to Lake Tyee in lieu
of outstanding balance amounts owed. (Motioned JW /2nd AW ) . After discussion,
the motion was amended to read: Motion made to authorize Janet Walsh to investigate and to execute quit claim
deeds for four lots in lieu of payment. (JA/AW) (MSC) approved as amended.
Don Miller, Lot 1-A-47
balance $462.58
Wayne Cattoni, 2-C-89, balance $689.52
Cameron Parkin, 1-A-46, balance $490.11
Huguette Cote, 2-A-72, balance $36.03
Marlene will contact the lot owners to tell them we accept their offer
to quit claim the property to come to the office to complete the quit claim document.
Meeting Adjourned: 3:22 p.m.
Janet Legg
Acting Secretary to the Board of Directors
Official December Board meeting minutes
Lake Tyee Board Meeting Minutes
Saturday,
December 19, 2009 at 9 a.m.
Lake Tyee Manager’s Office
Called to order at 9:05 a.m. by Peter Coates
Board Members Present: Janet Walsh (JW), Janet Legg (JL), Paula Ratcliff (PR) and Allen Ward (AW)
Resignation: Peter Coates announced Jean Johnson’s resignation from the Board effective immediately.
Additional Attendees: Marlene Lounsberry (ML) of CDC
Additions to Agenda: Audit, Installment Payments for 2010 Budget and Policies & Procedures PC announced
that the Board will have an executive session today to discuss Board appointments and have a discussion with a lot owner.
Approval of Minutes: November 14, 2009 Board Meeting Minutes (JL motioned,
2d AW) to approve minutes (MSC all); November 14, 2009 Executive Session minutes (JW motioned, 2d AW) to approve minutes (MSC
all) and December 12, 2009 Budget Ratification Meeting Minutes (JW motioned, 2d JL) to approve amended minutes (MSC all).
Peter apologized for misspeaking at the Budget Ratification Meeting when he incorrectly announced that the Budget had passed
by one vote.
Manager’s Report: CDC submitted a report of action items and a financial
narrative (attached).
- Ballot Recount completed on 12/18/2009:
2010 Ballot Ratification 174 yes and 388 no – passed
Electrical
Upgrade Special Assessment 106 yes and 453 no – failed. ML suggests the Board make a determination of what a valid
ballot is. A discrepancy report is available in the office for the Board to look at. - Shared Work Program has been approved by the Employment Security Department effective January 3, 2010.
- The number of comfort stations that need to be open is based on the number of people actually
here according to the Dept. of Health.
- Danger trees have been removed
except for three diseased trees in the Meadow. ML recommends we establish an annual contract for this service.
- Pitney Bowes has sent the information about canceling their contract. It will cost the
balance of the contract ($2,752.16) to settle it. The settlement amount is valid until January 2010.
- Bob Marshall submitted written verification of the donation of his 1993 Mercury Topaz to Lake
Tyee.
- The owner of 3B118 was sent a letter notifying them that they can
come before the Board at today’s meeting.
- Board applicant was notified
and agreed to be at Board meeting for interview regarding open Board position.
- Lot owner will meet with Board today be here to confirm his previous work agreement.
- P.O. Box has been closed and Lake Tyee has alerted CDC to the change of address and it will be posted on the web
page.
- Employee Paid Time Off Policy by CDC is that an employees vacation
must be used by end of year. ML recommends the Board allow time to carry over until end of March as summer vacation
is not allowed during summer months due to demand.
- Reciprocal lot use
– CDC will not agree to pay for the lot as it is being used by a CDC/Lake Tyee employee to the financial benefit of
Lake Tyee and not by CDC’s manager. If the trailer needs to be removed please advise ML and it will be removed.
- The attorney is prepared to do a Board Boot Camp and would like dates from the Board as to
when to schedule.
- Building moratorium can be lifted as the Covenant Review
Committee has resolved some of the issues regarding the restrictions on building. A new ACC form will be ready at January’s
Board Meeting for review and approval.
- Members in Good Standing Resolution
letters to be sent for hearing. Date to be set by Board
- Installment
Payment Resolution to be reviewed and voted on by Board
- Record Retention
Resolution regarding emails is already in place from previous Board.
- Electricity
Billing – the Board needs to determine if the electricity should be billed bi-monthly to save money on invoicing and
mailing. JW made a motion to go to bi-monthly electrical billing beginning January 2010, (PR 2d), (MSC all).
- Electrical Upgrade has been switched on and old system has been switched off. The employees
are moving meters to the new boxes and labeling them with the lot numbers.
- Manager’s
Q&A with lot owners will be held on the 2nd Saturday of each month at 11 a.m. in the clubhouse. January 9th will
be the first meeting and a Board member will be in attendance at all of them. This will be posted to website.
- By general consensus, it was agreed that due to this year’s financial situation, holiday
compensation for employees will not occur. PC will draft a letter to them expressing our gratitude.
- January billing for dues to include all payment options with specific amounts and notification
that we will be billing electricity on a bi-monthly basis.
Treasurer’s
Report for November, 2009 (ML for JL): - General Operating Account balance:
$132,475.93
- Accounts Payable: $52,565.52; Prepaid Assessments $28,961.15;
Bank Loan on Mobile $30,416.36
- $295,439.10 due to Reserve from Operating
and $226,394.24 due to Operating from Reserve
(these were balance forward
entry corrections made when the three sets of 2008 books were reconciled into one). The difference of $69,044.86 is
what Operation owes Reserve except that as of 12/31/2008 there is still about $38,000 unpaid from the 2008 receivables.
Barb advised the money needs to be moved by the end of the year if funds are available. - Replacement Reserves – Maintenance Reserve Account balance: $146,675.60
- Assessments Receivable: $200,940.88
- Delinquent Accounts:
82 accounts at the attorney. ML beleives90 liens have been filed but she will double check that.
- Major Expense Items of Note for November: Electrical System Repair $24,630; septic repair
$2,155 and equipment maintenance $1,027.
JW requested a copy of liens
for the Board if there is no additional charge. ML will ask. Installment Payment Resolution (attached): PC
read the Installment Payment Resolution and amended the last line, changing the date to February, 2010. Motion to approve
as amended (JW motion), (JL 2d), (MSC, all) Meeting adjourned at 9:57 for Lot Owner Meeting and Executive Session.Board
Meeting reconvened at 11:30 a.m.
Committee Reports
Electrical Project Update: (Pat Sweeney) Allen Ward is now the Board Liaison and will
advise Pat of the next scheduled meeting date.
Recreation and Social: (Angel Hanson) Barb reported the New Year’s Eve party has
been scheduled.
Grounds
and Maintenance: (Peter Coates) Committee will reconvene in January.
Building & Covenant: (?)Covenant Review Committee (Paula Ratcliff) Committee
met November 14. Minutes of that meeting were dispersed to the Board. Allen will email Ed Forshee to ask if he
is willing to amend the 96 covenants to bring the building portion of them into compliance.
Budget & Finance: (Barb Thibert)
PC took the opportunity to thank Alex Thibert for all of his work on the sound system and wiring in the clubhouse.·Unfavorable Budget Variance by years end: $52,956 shortfall ($31,000 was factored in
to the $400 special assessment. The other $20,000 needs to be funded by either adjusting budget, spending less, possible
additional special assessments, hopefully delinquencies will be paid up etc.).·
Lots with a balance greater than 90 days has jumped from 149 in October to 163 in November·
There are 199 delinquent lots total
Unfinished Business Comfort
Stations: SKR#14831 (pg. 3) states: Central Facility Buildings shall be located within a maximum distance
of 400’ from each lot.
Mobile Interest Rate: JL spoke
to Jim Bishop who advised her that he believes we can get a reduced interest rate without refinancing. He has promised
to call her back next week with confirmation.
Hearing Committee for
Violations: PC advised the hearing will take place at 9 a.m. February 27th with Board Meeting at 10 a.m. Quit Claim
In Lieu of Foreclosure: ML advised that CDC’s attorney can include it in the demand letter.ML will bring in copies
of the letters for us to look at to determine which one to include the option to Quit Claim their property in.
Website Design: Colleen has asked for a Board position on a “lots for sale by owner”
web page. The Board has agreed to give her the go ahead for the web page, however, the seller will need to come into
the office and sign a form that clearly states their role and responsibility in using the site and complying with the rules
set forth by the Board as stated at last month’s Board meeting. Colleen’s question regarding lots listed
by an owner whose lot is also listed with Lands West. Regardless of who sells lot, if the lot is listed at Lands West,
they would receive the commission. Lands West can put as many lots on Lake Tyee’s website as they want to.
New Business Suspension of Member in Good Standing Status Resolution
(attached): a motion made and read by JW to adopt, (JL 2d) and approved (MSC, all). Hearing date set 1/23 at 9
a.m.. Notice must be sent 14 days prior to meeting and be certified or registered with return receipt required. ML to
send asap. She will advise Board the proxies that will be pulled prior to the next vote.
Ballots: ML asked the Board to create a policy for what we consider to be acceptable and valid ballots.
She had to contact general counsel regarding ballots and proxies received for same lot. ML was advised that whatever
is received first is the valid vote unless a written request is received from lot owner. ML advised that under Roberts
Rules of Order, adjustments to ballots that are made after results are announced are not counted. PC advised ML to add
an additional line to ballots for lot owners to print their name. JW suggested a label go onto ballots that include
lot owner name and lot number for better readability.
2009 Audit:
JL asked ML to approach the current auditor for a bid to do the 2009 audit so the report would be available for the June 2010
Annual Meeting.
Electrical Upgrade Special Assessment: Motion
made by Janet Walsh that the finance committee goes back and gets updated figures for a proposed three-year plan which the
Board will assess in a one-time amount, with a clause for a final completion assessment in the third and final year (PR 2nd)
and passed (MSC, all). Primary meeting date January 30th and February 13th is the secondary meeting date. PC requested
PR to forward motion to Pat Sweeney. Media & Video Taping of Meetings: JW read bylaw 4.5.3
Lot Owner Q&A: Need volunteer board member to attend 1/9 meeting. Board member
will bring any board issue back for discussion at next board meeting. No minutes will be taken.
Skagit County Equipment in the yard: PC advised JW county is just staging it here instead
of hauling it back and forth.
Tree Removal Expense: JW asked
why we are still spending money when we’re so close to not making the year end. ML advised the liability far exceeds
the cost of removing the trees. PC advised tree removal had been previously approved. An arborist is used to determine
danger trees. ML advised staff is not doing any work that costs a lot of money. They are basically doing only
labor intensive work. The septic lid was broken and a liability so that did need to be replaced.
Tool Donation: ML advised no tools have been donated yet. ML has list and she will
forward to Colleen to have her post it to website. PC plans to contact Colleen as well.
Request for invoices from and checks written to CDC: JL asked if we could fulfill request by emailing lot owner
PDF file. Due to account numbers included, it was determined we cannot do that. PC advised ML that we need to
know specifics of request. At that time, CDC can make a recommendation to the Board advising us if proprietary information
is being requested that cannot be turned over.
Board Meetings: January 23rd at 10 a.m. and January 30th or February
13th for Electrical Upgrade Special Assessment
Meeting adjourned at 3:03 p.m. Paula RatcliffBoard Secretary
November Board Meeting
minutes
Lake Tyee Board Meeting Minutes
Saturday, November 14, 2009 at 9 a.m.
Lake Tyee Manager’s Office
Called to order at 9 a.m. by Janet Walsh
Board
Members Present: Janet Walsh (JW), Janet Legg (JL), Paula Ratcliff (PR) and Allen Ward
(AW)
Absent: Peter Coates and Jean Johnson
Additional Attendees: Marlene Lounsberry (ML) of CDC
Additions to Agenda: Collen McKnight re: website
JW announced that an executive session would commence after adjournment of today’s board
meeting to discuss legal issues.
Approval of Minutes:
October 24, 2009 (PR motioned, 2d JL) to approve minutes (MSC all); October 24, 2009 Executive Session (JW motioned, 2d PR)
to approve minutes (MSC all).
Manager’s Report: CDC
submitted a report of action items and a financial narrative (attached).
- Recent break-ins mainly to sheds.
- Board
members who wish to review rental agreement of mobile home may do so in office.
- Free sandbags (2500) available for Meadow lot owners to place around their structures. No sandbagging allowed
along bank of creek. Permit is required before culvert is installed.
- Electrical upgrade completed in 2C area. Letters were sent to lot owners who were not in compliance with the
September 30th cut-over date. It was decided not to send a second letter.
Pat stated the inspectors will inspect the secondary in two weeks. Anyone not in compliance
will not be able to hook up to new system as their boxes will be locked. PR suggested that those lots who have
had locks put on their boxes be checked to be sure no one has hooked up to the new system illegally. ML agreed to do
so and Pat will supply her with a list.
- Site inspection was completed
and 56 total violation letters will be sent out. Out of those, nine had some form of a collapsed structure on them.
Pictures of the collapses available in the office. One lot owner has a personal hardship and ML feels this would be
a great opportunity for volunteers to go out and clean up the lot. ML will contact Colleen to put this and other volunteer
projects on the website.
- Quit Claim Process: she is still waiting
to hear back from the attorney.
- Power Grant: available but we
need to show that our project improves efficiency. Pat contacted North Sky and they are drafting a letter for us.
- Emails and phone log available in the office showing feedback from lot owners.
- Would like a 6-month building moratorium until Covenant issues are resolved.
She believes we need an enforceable building process in place before anymore building is allowed. Covenants are currently
in the hands of the attorneys. Goth & DeWalt recommends a Property Law or Development Attorney (possibly Vince Pillis)
be contacted. ML will contact him about his fees and email the board.
- Employee
training completed last week and expectations given to conserve where they can.
- Looking at alternative energy-efficient lighting options as some of the light stands are ready to fall over.
Treasurer’s Report for October,
2009 (ML for JL):
- General Operating Account balance:
$36,267.47
- Accounts Payable: $21,975.97
- $295,439.10 due to Reserve from Operating and $226,394.24 due to Operating from Reserve
(these were balance forward entry corrections made when the three sets
of 2008 books were reconciled into one). The difference of $69,044.86 is what Operation owes Reserve except that as
of 12/31/2008 there were still about $38,000 unpaid from the 2008 receivables. Some may have been paid in 2009 but some
may still be delinquent. Barb reported that this was due to the 2008 electrical special assessment. The monies
were not deposited into the Reserve account but in the Operating account. When the electrical was paid for, it was paid
out of the Operating account but there was a surplus between the amount assessed and the final expense which is about $70,000.
That money needs to be moved from Operation to Reserve. In 2009, we funded Reserves as if 100% of the people paid.
The reason is that we have a contractual obligation to pay the vendor. So even though the total amount wasn’t
collected in 2008, the total amount should be moved to fund the Reserve. The Board cannot transfer the money into Reserve
at this time because we don’t have it. As the $400 assessments are paid, possibly by the end of December, we can
transfer the money into Reserve.
- an email from the attorney
was received with an update of the delinquent accounts. She will forward to the Board.
- ML asked the Board if CDC can give Barb a complete financial package electronically.
(JL motioned, AW 2d) allowing CDC to electronically send to Barb a complete financial package
(MSC all).
Committee Reports
Electrical Project Update (Pat Sweeney)
Pat met with Potelco yesterday and there will be two transformers that need to be palletized and
stored somewhere out of the weather.
Recreation and Social (Angel Hanson)
Barb reported there were about 100 people at the Halloween party. Planning is underway for the
New Year’s Eve party but consideration for our electrical situation
will need to be taken into
account.
Grounds and Maintenance: no report
Building & Covenant:
no report
Budget & Finance
(Barb Thibert)
- Annual Operating Assessment: will contact
CDC about the difference
- Late Charges: $22,520 has been billed
thus far this year, however, it is probably not all collectible due to delinquencies
- Total Salaries & Wages: we have spent 80% of this budget so far and will likely use the balance available
by year’s end.
- Legal Collection Attorney Fees: spent $23,382
in attorney fees so far due to collection process. Of that, $9000 was spent just in the month of October. These
fees will get billed back to the lot owners.
- Road Repair & Maintenance:
$3,125 was for work done on Tillamook and gravel
- Equipment Repair &
Maintenance: $12,392 spent although $5,000 was budgeted
- Operating
Net Loss: Expecting to be over-budget $55,063 by end of year.
- Accounts
Receivable: improvement from September to October. Eleven lots have paid something to remove them from the greater
than 90 days balance.
- Lots with a credit balance rose from $12,038
in September to $52,181 in October mainly due to lot owners paying $400 assessment in full. This allowed us to pay our
bills and not pay late fees or finance charges.
- Statement of Reserves:
Due to unforeseen electrical system repairs there will be a negative $20,123 in reserves. JW made a motion to reallocate
$25,000 from the Lake Reserve to Electrical Project Reserve (PR 2d, MSC all).
- PR made a motion to move $50,000 out of Unallocated Reserve to Electrical Project Reserve and as the money from 2010
is collected, would go back into Unallocated (JW 2d , MSC all).
- Operations
Cash Flow Projection: collected more money and paid out less primarily because of the nearly 100 lot owners paid the
$400 assessment in full.
Meeting adjourned at 10 a.m.
for Lot Owner meeting in clubhouse. Board meeting reconvened at 1:30.
Unfinished Business
Website
Design: Colleen asked to post lots for sale on the website. JW advised the following stipulations:
1) at no time will the Lake Tyee Business Office facilitate the showing of the property or allow gate access to anyone
looking at those lots 2) lot owners will be 100% responsible for showing their lots 3) site will show lot number with
a short description, price and contact number only. 4) lot owners need to know that if they choose to post their property,
the moment anyone contacts the Business Office regarding it, their post will be removed.
Colleen will post a disclaimer stating: 1) the lot owner must meet their prospective buyer at the
gate
2) only the lot owner can let them in the gate 3) lot owner
is to stay with the prospective buyer the entire time and then escort them out through the gate. She will get Board
approval prior to posting the disclaimer. Pictures of property will not be posted on the site. It was decided
that the issue needs to be discussed further and this will be put on next month’s agenda. A policy statement is
being worked on by Paula and Colleen. It will be put on December’s agenda to be voted on.
Lot owners want to know what the weather and temperature is at Lake Tyee, not just the temperature
in Concrete. Colleen will ask Wendy if she will submit this information on a volunteer basis.
Colleen will email the cost (about $200) of the website for the next year to CDC and it needs
to be paid by December 18.
Colleen was advised not to edit approved
board minutes; they need to be posted as they are.
Grading
and Fill Permits: PR contacted Skagit County, grading and fill permits are required and are available online.
ML will include this information in building permit process. JW made a motion to suspend approval of future building
permits until April 1, 2010 with CDC’s guarantee that they will have a revised building permit application process approved
by that time. After discussion, the motion was amended and the date from April 1 to March 1, 2010. (JL 2d the amendment,
MSC all)
Comfort Stations: PR was advised
by Skagit County that unless the plat map specifies that we are required to keep 16 comfort stations, we are not obligated
to do so (it is usually written around the edge of the map. Plat maps that were looked at this morning showed no information
regarding this. ML will check with the Health Department to see if there is a requirement, based on population, of the
number of comfort stations we need to have. JW will go to the County Planning Department and look at the original plat
map and review it with someone there to determine if there is a stipulation about the number of comfort stations we have to
keep perpetually.
Covenants: ML volunteered
to go to the County and get copies of all the documents. Dan from Lands West advised us that two years ago Ed was told
by the County that the documents were not just Covenants but Plat Restrictions. To change them requires a 100% vote
to do so because when someone buys into Lake Tyee, they are not just to abide by the Covenants but be protected by them as
well. Ed will be back this summer and will probably be willing to talk to the Board about it again.
ML advised the Board that you can take as long as you need to get the 100% by going door-to-door,
lot-to-lot, etc.
Mobile Interest Rate: JL
advised our loan interest rate is 10.5%. The loan officer didn’t think rate could be lowered unless we refinanced
but he is checking into it and is to contact JL next week with an answer.
Vacant Board Positions: ML will advise lot owners that the Board is still considering applicants
and that is not too late to apply. This will be posted on website, email, on gates and restrooms. ML will send
a thank you letter to the lot owner who applied but can’t make meetings. ML will contact Ron Harczo to meet with
the Board in Executive Session after next month’s Board meeting.
CDC
Contract Renegotiations: Board will continue to email each another. This will be discussed in December’s
Executive Session. AW will contact Ed Forshee for any recommendations he may have because he has written many of these
types of contracts.
Member In Good Standing: ML
contacted Goth & DeWalt and after reading our Bylaws a lot owner does not have to have a hearing if it is just a dues
assessment or delinquency. If anything on their account is delinquent, a hearing is not needed to have their member-in-good-standing
status be rescinded. If they are in violation of a rule or guideline, then they must have a hearing in order for their
member-in-good-standing status to be revoked. Marlene also stated the attorney advised that the general rule for delinquency
is 30 days. He is sending the above to Anita via email and then she will forward it to the Board. Barb mentioned
that the previous Board had agreed that even though a bill is due on the 15th, it doesn’t become delinquent
until the 30th of the month. We should know by December 1st who is delinquent but because of CDC’s
process of posting the accounts, it will probably be closer to the 12th. ML will run an accurate delinquency report
dated December 11 at 5 p.m. Every payment that has been posted will be on the report. However, if a payment is in a
lock box in Sacramento, we have no way of knowing that. If a lot owner comes to the meeting with check in hand, we cannot
accept it as it has to be turned over to the attorney. A lot owner’s key is not turned off until their balance
owing is $300. BT advised the amount of $300 was chosen because it is just shy of two months dues. If it was set
any lower, it could cause problems because it may be a timing issue of CDC’s processing of the payment. Barb asked
if ML could ask the attorney if we could put a deadline date that is prior to the date of a future vote such as November 30th
or December 5th.
Reciprocal Lot: JW wanted to clarify the proposal that Anita had made and whether
or not it needs to be agreed upon formally. ML will contact Anita because an employee is now living in the RV.
ML will include the findings in her Manager’s Report next month.
Quit Claim: ML is waiting for the attorney to get back to her.
JW would like to include in that process the fee for a title search. Dan advised the cost is approximately $250.
JW suggested the Board needs to determine if Lake Tyee or the lot owner would pay for the title search. Barb advised
us that Ed had contacted her about lot owners who may want to Quit Claim their property to Lands West. Barb is concerned
because time is of the essence for a process to be in place. If lot owners choose to do Quit Claim to Lands West then
we will lose the assessment because a lien will not be put on those properties until the vote on December 12th. Lands
West does not pay assessments and if they hold title, we lose that money. However, any money owed to Lake Tyee at the
time of the Quit Claim will be paid to Lake Tyee. Lands West currently does their own title searches by checking Skagit
County records for registered liens and will check the home property as well. If none are found, they are fairly confident
there aren’t any. They then check with Lake Tyee to see if anything is owed. As JL pointed out, there may
be liens on property that the lot owner isn’t even aware of. JL contacted a title company and explained what was
going on and they told her that we need to go through an attorney for advice. JL believes we need to just pay the $250
per lot for a title search, otherwise, the lot owner will probably Quit Claim it elsewhere.
JW advised ML that if she gets any serious Quit Claim offers between now and the vote, that she is to
advise the Board immediately and it would probably be worth our while to pay the $250 for the title search and get the property
back. Barb suggested a document be available for the lot owner to sign that if they should change their mind about Quit
Claiming property, that they will reimburse us the $250 title search fee.
Budget & Finance continued
At the
December 12th Budget Ratification Meeting Barb will present to the lot owners:
- the 2010 Budget process by the committee
- present
documentation of all the communication with the lot owners regarding the finances
- Pat Sweeney’s Electrical Project Presentation if he wants to do it again or we can email it to those who want
it. Barb will ask him about this.
- will go over the more expensive
costs such as payroll, CDC management, office expenses
- Reserves and
Reserve Study
- collection costs and credit card fees
- maintenance projects that ML wants to tackle in 2010 such as culverts, pit, trees, etc.
- Future needs that ML knows of beyond 2010 such as a building replacement, dustless,
etc.
- Electricity Project and why it is not included in the 2010 Budget
Barb asks that we reevaluate whether or not we need to bill
on a monthly basis for electricity. JW suggested now that we’ve paid for common area electricity for a year, isn’t
it possible to project what they will owe and bill quarterly to save in billing costs. The largest electrical bill last
year was $15,000 so even if we had to add an extra billing to cover a large cost like that, we would still be saving money.
JW suggested that meters could be read bi-monthly instead of monthly as well.
ML
advised that the meters can be read in a day and a half…except if there is snow on the ground.
Barb will do some analysis on this and email it to the Board. She also wants to look at a third-party
electronic billing service in the future.
New Business - none
Board Meetings: December 12th Budget
Ratification Meeting and December 19th Board Meeting
Meeting adjourned at 3:03 p.m. by AW to go into Executive Session.
Paula Ratcliff
Board
Secretary
October Board Meeting
minutes
Lake Tyee Board Meeting Minutes
Saturday, October 24, 2009 at 9 a.m.
Lake Tyee Manager’s Office
Called to
order at 9:10 a.m. by Peter Coates
Board Members Present: Peter Coates
(PC), Janet Walsh (JW), Janet Legg (JL),
Paula Ratcliff (PR)
Absent: Jean Johnson (JJ) Jean joined meeting at 9:30.
Additional
Attendees: Marlene Lounsberry (ML) of CDC
Additions to Agenda:
None, however, Peter requested Barb give the Budget & Finance Committee Report at this time.
Budget & Finance Committee Report: Barb handed out a new report that will be generated
by CDC on a monthly basis showing the status of lots with balances owing over 90 days and the status of each (attached). AR
Risk Report reviewed and attached. Peter announced that the 2009 Electrical Project cost was lowered from $201,252 to
$185,999.05.
Approval of Minutes: August 22, 2009 Executive Board Meeting
Minutes (JW motioned, 2nd JJ) to approve minutes (MSC all); September 26, 2009 Board Meeting Minutes (JJ motioned, 2nd JW)
to approve minutes (MSC all).
Manager’s
Report: CDC submitted a report of action items and a financial narrative (attached).
Storm Damage: power out in most of the park and a tree fell on trailer
at 2C63 last night.
Removal of Danger Trees: Randy from Safety Tree Service
bid $1600/day and probably 2 ½ days to complete work. Peter advised money to pay for removal of trees can come
out of general reserves. Paula asked Marlene to find out what it would cost to renew Randy’s arborist license.
Others want to bid for the work but they need to be bonded and a contract established with them that outlines their clean-up
practices.
Hearing Meetings for Violations: Paula asked Marlene if
the violation letter CDC sends out to lot owners already has the information on them regarding the date of a hearing?
Marlene advised that to be correct.
Bank Signature Cards: Signed by
Peter Coates, Janet Walsh, Janet Legg and Paula Ratcliff
Permanent Structure: Marlene
is getting conflicting reports from L & I regarding what they deem to be permanent structures. This is still being
looked into.
Septic Tanks: powdered detergent is being found in septic
tanks. Marlene requested maintenance to determine what lots use that particular septic tank and letters sent out to
them. Paula advised this info should be in Welcome Packet as well. Evidently, Janet Legg is updating the packet
for new lot owners.
Protocol for Emergencies (power, water, electric):
contact Tammy Smith > she contacts Marlene > she contacts Peter.
Road
to upper park: will be closed at first snow. Notification will be on website and in billing packet. Peter
also stated that lot owners be notified in the next billing that we will do our best to clear primary roads of snow.
Primary Focus for Fall and Winter: ditches, drainage and roads.
Property Tours: Peter advised that he, Doug and Marlene tour Lake Tyee each week and would like anyone from
the Board or Grounds & Maintenance Committee to join them.
Old Business
Website Design: Colleen provided the Board with various
ideas for our website. She is going to try to get the Lake Tyee logo back on the homepage. She would like electrical
updates from Pat Sweeney and suggests the Board look at Black Mountain site. It was agreed to allow lot owner notes
be used to create a Question & Answer page. Notes will not be posted but frequently asked questions along with answers
from the Board will be. Colleen will use her discretion on this and will run any questionable issue by the Board first.
Anita suggested that if she has not received a reply from the Board that it is okay to post after 24 hours. Opportunities
for volunteers will fall under the Grounds & Maintenance Committee. They will put together project-specific volunteer
opportunities with dates for Colleen. Dan from LandsWest approved a laketyee.com. Anita to provide links for RCW 64.38 and RCW 24.03
Board
Meeting adjourned at 9:55 a.m. for Lot Owner Meeting and subsequent Executive Session to discuss legal issues. Board
reconvened in regular session at 1:45 p.m.
Committee Reports
Treasurer’s Report for September, 2009 (Janet Legg):
General
Operating Account Balance:
Accounts Receivable $44,758
Accounts Payable $28,000
Replacement Reserves
$336,894 ($29,000 not transferred to reserves in September)
Assessment
Receivables $165,000
Delinquent Accounts
160 lots delinquent over 90 days for a total of $154,000.00
(JL) advised Board
there is enough money in reserves to cover electrical expenses to date.
Peter
spoke to Pat Sweeney who advised him significant Potelco bills will be due early November and early December for electrical.
Marlene advised the October Potelco bill for $185,999 will be paid in November. Current electrical: $280,000 for
upper park, $100,000 west side of lake, $25,000 east side of lake. Total $365,000 (money to pay for these is coming
from $400 assessment). Board can transfer from one reserve to another reserve. Anita advised the park cannot be
closed down because it belongs to the lot owners. Attorney needs to be asked about the possibility on Monday.
Old Business continued
Decisions made by Board regarding
the 2010 Budget:
Line item #82 needs to be addressed. Janet Legg
will send info to Board on Monday.
Lot owners are requested to submit
their questions to the office so the Board is prepared to answer them at the Budget Ratification meeting. The meeting
will be held on December 12th. Sign-in begins at 9 a.m. and the meeting to start promptly at 10 a.m. in the clubhouse.
Decisions made by Board regarding the 2010 Detailed Budget & Summary Reports:
add total amount of assessment to $688,900
Delete September 2009 YTD column
Move “Total
2010 Annual Dues” to bottom of page
The Operating and Reserve
Budget Summary reports and ballot will be mailed out to lot owners this week. If a lot owner desires a copy of the detail
budget, it can be emailed, mailed
Janet Legg to advise Barb of changes
to be made and to have Barb provide Marlene with amended reports. Marlene will forward to Board.
Decisions made by Board regarding the Electrical Upgrade Project:
A one-year plan
The Electrical Project and 2010 Budget will
be voted on separately by lot owners.
The Electrical Project Overview
and Budget reports, the revised Electrical Upgrade Project Informational sheet with ballot to be mailed out this week.
A 25% delinquency contingency will be used and the Board will decide what will happen to any leftover
money at the conclusion of the project.
Board reviewed Lake Tyee Electrical
Upgrade Project information sheet that will be sent to lot owners and it was agreed
Paragraph 3: change amount to $152,920 and recalculate
to $154 per lot
Paragraph 4, the second sentence will read:
We must rely on our owners to individually fund/finance their portion of the project through whatever financial means are
available to them.
Paragraph 5, last sentence: is to be eliminated
entirely.
Rename to Electrical Upgrade Project Completion Report
A motion made by PC: On the February 1st, 2010,
billing the Lake Tyee lot owners will be assessed $4,470 for each lot for cost of electrical upgrade project as proposed.
JJ 2nd, MSC all
$4,470 electrical assessment is due February 15, 2010.
The amended Lake Tyee Electrical Upgrade Completion Project report
will be mailed out November 1 with 2010 Budget information and ballots.
CDC
will email Board with all info for review prior to mail out
CDC to
mail out next week.
Due Process: Marlene will choose a hearing date for 3B118 along with any other violations and advise committee.
Amended Meeting Minute Dates: Today’s approval of minutes were for the August 29 Executive
Session and September 26 Board Meeting.
Grading and Fill Permits: Jean
is to call County Monday and email Board.
Mobile Interest Rate: JL will
call bank to find out if we can get a lower interest rate on mobile
Vacant
Board Positions: Motion made by PC to appoint Allen Ward to one of the vacated Board positions per Bylaw 5.4.
JL 2nd, (MSC) all. No additional decisions made on other board applications.
Lake
Tyee Owned Lots: the Board had previously authorized CDC to survey center pins and clean up lots in preparation to sell
in the spring. We are now revisiting this due to cost. Dan from LandsWest advised he knows that one center pin
is on a lot and possibly the other two as well. Lot-to-Lot measurements may also be used to locate pins on other two.
He has a metal detector that can be used. If a survey is required the cost is $350 per lot. Lot owners who desire
to have their lot surveyed at the same time and same price can request to do so. Information will be put on website.
Work Camper: PC made a motion that Board allow CDC to initiate the process and authorize
them to incur cost of online subscription up to $150 for the purpose of acquiring work campers for 2010 season. JJ 2nd,
MSC all. Marlene to recommend to Board how many lots she wants to use for work campers.
New Business
Tool List: to be posted to website and clubhouse.
ML will make sure Lake Tyee tools are marked appropriately.
Neglected Lots:
The Board has asked Marlene to give us a list of lots that are in violation. Board will notify lot owner by certified
mail and allow them time to clean up property themselves. Otherwise, our staff will clean up the lot and bill the lot
owner.
3A83: Board will send letter to lot owner requesting deed in lieu
of foreclosure (balance owing is $6561). Marlene will ask Anita for a generic letter we can use for this purpose
Live-Ins: in violation of Skagit County Ordinance.
Post Office Box: Lake Tyee has a mail box here so P.O. Box 569 will be closed. Paula is to forward minutes
to Jean and she will take to Post Office to close box.
Upcoming Board
Meetings: PC made a motion to change the November Board meeting to the 14th, the Budget Ratification meeting on December
12th and the December Board meeting on the 19th. JJ 2d, MSC all. These date changes to go on website.
Conference Call October 26 at 1:30 p.m.: to discuss lawsuit, initial negotiation of CDC
contract and rental agreement.
Lot Owner Meetings: Marlene will take
over lot owner meetings as of January 2010. They will most likely take place two weeks prior to Board meeting with a
Board member present.
Gravel Pit: Dan from LandsWest was asked
if they restructured pit and he advised Board that they had. JW made a motion to close pit to all contractors and heavy
equipment for next 90 days. (JJ 2nd), (MSC all). Lot owners can get no more than one pickup truck load and do
so at their own risk. In the meantime, CDC will ask Dan to take Billy to view pit and determine if it is safe.
Areas of concern will be flagged.
Manager’s Rental: JW made the
following motion: to increase the rent to $720/month for the next 24 months and tenant would have to agree to a payroll
deduction. JJ 2nd, (MSC) all.
Meeting adjourned 4:30 p.m.
Paula Ratcliff
Board Secretary